When will U.S. Highway 10 be free of construction?

Two projects in Waupaca County will extend into 2027

Posted

WAUPACA COUNTY – Motorists along U.S. 10 in Waupaca County will see construction barrels come down later this month, though two of the corridor’s three road projects will stretch into 2027 due to expanded repair needs and deteriorating pavement, according to the Wisconsin Department of Transportation (DOT).

DOT Project Manager Wendy Arneson said expanded concrete repair needs pushed remaining bridge work on one segment into next spring, while worsening road conditions prompted the agency to move a separate 2027 project up to this fall.

Traffic control devices are scheduled to come down by Friday on two segments and by Nov. 27 on the third. Once those devices are removed, Arneson said full standard lane configurations and normal posted speed limits will be restored for the entire winter.

Arneson said the $4.4 million project between Anderson Road and Appletree Lane saw its overall schedule extended after crews identified additional concrete pavement repairs during construction, increasing the scope of work.

Crews are finishing diamond-grinding concrete pavement repairs, routing and sealing the joint between the concrete pavement and asphalt shoulder, and installing pavement markings and rumble strips before removing traffic control devices by Nov. 27, the DOT said.

Because winter weather was approaching, and remaining bridge deck, overlay and shoulder repairs are weather-dependent, the project team determined those tasks were “not critical to maintaining safe roadway conditions” and postponed them until spring 2027, Arneson said.

Crews are scheduled to return in April to replace concrete approach slabs at the westbound U.S. 10 bridges over the Crystal River and Wis. 49/54, place a polymer overlay on the westbound bridge over Wis. 22, repair the westbound bridge over Wis. 49/54 and complete additional concrete and asphalt shoulder repairs, according to the DOT. Work on that section is expected to finish by April 30, 2027, though Arneson said schedules could fluctuate depending on spring weather conditions and crew availability.

A second $7.6 million project on westbound U.S. 10 from Appletree Lane to Old Wis. 49 was originally slated to start in 2027, but WisDOT moved the work up into 2026 due to “accelerated deterioration of the existing concrete pavement,” Arneson said. That work is expected to wrap up this week.

When crews return in 2027, they will replace concrete in the U.S. 10 travel lanes, repave asphalt shoulders and replace guardrails, according to the DOT. The work will also include replacing bridge approaches, guardrails and part of a shared-use path on County A/Wis. 22, as well as milling and repaving between the County X ramp terminals.

U.S. 10 will remain open with lane closures during construction, including a spring 2027 head-to-head crossover pattern shifting eastbound traffic onto westbound lanes that is scheduled to be removed before Memorial Day weekend, Arneson said.

Intermittent closures with signed detour routes are also planned for the eastbound on- and off-ramps at County X, the eastbound on- and off-ramps at County A and the westbound on-ramp at County A, with full project completion anticipated by next fall depending on roadway conditions and any additional repairs identified during construction, Arneson said.

The third segment, a $3.6 million project on westbound U.S. 10 from Old Wis. 49 to the Winnebago County line, remains set to finish this week.

U.S. Highway 10, construction, Waupaca County